Phase one consisted of 50 houses on the outskirts of Carrick on Suir in Tipperary. Eventually the development will consist of 250 Houses. All the site services have been installed. The Houses have a natural gas installation. All houses have a weather compensation heating system

Full M+E Design including Natural Gas, Eircom, ESB Site power and Public Lighting, Chorus, Internal M+E design on houses.

 

Name of Project: Carrick-on-Suir Housing

Client: Cumbarwall Construction

 

Description of Role:

Mechanical and Electrical Services Consultants

Total Capital Value:

€3.5m

Dates of Involvement:

2006-2007

 
Design Team:

John Hayes – Managing Partner

Shane Tierney – M&E Director